Fulan Offshore’s CLB Ai Lan Yi Hao (AL-1) has recently completed the installation of the first circuit of the 500kV export cable for the Yangjiang Fanshi-1 Offshore Windfarm Development Project in Guangdong, China.

The Fanshi-1 Project comprises two circuits of the 500kV export cable between the offshore substation and the interim compensation station; each circuit is about 80km long, setting the industry record for the longest 500kV AC subsea cable.

This sets a new benchmark for the deep-water development vision of the China Domestic OWF market.

This is also Fulan Offshore’s first track record in installing a 500kV HVAC subsea cable.

The 2nd circuit has been loaded onto a cable-lay vessel with a more powerful DP2 system to withstand severe winter conditions; the target is to commission the project before the end of 2025. 500kV subsea cable technology is becoming mature and increasingly common in China’s domestic OWF industry.

Original announcement: Fulan Offshore
Image: Courtesy of Fulan Offshore

Explore more Subsea news


This article has been selected for publication by the Cable Technology News Editorial Team based on its relevance and significance to the global cable, power, energy, subsea and optical fibre industries.

Cable Technology News publishes major industry developments from across the sector, including organisations that are not commercial partners, where we believe the news is of genuine interest to our readership.

Publication does not constitute an endorsement of any company, product or service.

Interested in raising your organisation’s profile across the global cable industry?

Explore our annual industry partnerships here.